As Director of Network Deployment at Exario Networks I took over responsibility for design, cage space contract negotiation, hardware purchase, installation, and turn-up of Exario's data center co-location cage space. The pictures below are of the Denver, Colorado installation. The site was taken from empty floor space to live POP in 5 days by one Network Technician and myself. All construction, including rack erection, hardware instillation, power distribution, and copper, coax, and fiber cabling was done by us. At that time we were the only company to self-install a Tellabs Titan DACS.

denver1.jpg
denver2.jpg
denver3.jpg
denver4.jpg
denver5.jpg
denver6.jpg
denver7.jpg
denver8.jpg

Return to Projects Page